bp completes Central Azeri platform maintenance ahead of schedule

bp completes Central Azeri platform maintenance ahead of schedule

azernews.az 26.08.2026 13:45 1 baxış
bp as operator of the Azeri-Chirag-Deepwater Gunashli (ACG) field development project advises that the planned maintenance programme (turnaround - TAR) on the Central Azeri platform, which started on 19 August and was pl